Gypsy Corner

J025E – Shurgard Gypsy Corner for FK Howard was completed on site this Friday the 4th of March.
An L shape stick and beam structure against an existing building compromising of 120 tonnes hot rolled steelwork, 6 tonnes of cold rolled purlins & side rails, and 7 tonnes of cold rolled floor joists.
Steelwork was delivered to site on an 8-week lead time as agreed, however installation was completed 1 week early thanks to our sub-contractors Sheen Valley Properties.